MPS: Order Release & Past Actual
この製品はもう使用できません。
STORY BEHIND THE FEATURES
ODOO'S FUNCTIONS
CLUEDOO'S FUNCTIONS
CLUEDOO RECOMMENDATION
Install this tool in 100% of your databases to enhance the functionality of the Master Production Schedule, providing a useful and valuable improvement.
HOW TO USE THIS MODULE
1. Past Actual Detail about module on actual replenishment of the first month of the MPS, take this month + the past and not only this month. Example: MPS start in June. I have in my system a receipt planned for May of qty 50. ODS => on June, nothing planned so actual = 0. Cluedoo => give the visibility on the MPS that we have 0 for June but 50 in May (of RFQ - Receipts - MO - ...).
1.1 Go to MPS > Click on the number in "Actual / Suggested Replenishment" line > Create RFQ/Receipt/MO | ||
1.2 Create new RFQ > Fill Vendor (set in Purchase tab of Product) > Set qty and Order Deadline/Expected Arrival > Confirm For ex: I set 1 qty, vendor: Lumber Inc and expected arrival is 20/05 | ||
1.3 Go back to MPS > you can check that the receipts increase from 101 to 102 | ||
2. Order Release (there is the improvement in module fal_mps_forecast_demand) Principle: Add row Forecasted Order Release in MPS, and base on the suggested replenishment and the leadtime to calculate this field You will have this line when go to Rows > Check Forecasted Order Release | ||
2.1 Before: we have 12 in Sep 2024 and 13 in Oct 2024 because Delivery lead time of Lumber Inc is 0 | ||
2.2 Go to product information by click on the name of product > go to purchase's tab then change Delivery Lead time of vendor: Lumeber Inc to 30 days | ||
2.3 Go back to MPS and the qty change from Sep&Oct to Aug&Sep (1 month before) |